A contractor estimates that he can complete a job with 15 people in 40 days. After 12 days, the work stopped for 7 days due to some reason. To complete the job on time, how many more workers need to be added?
To complete the job on time, the contractor needs to add more workers to the team. If the work stopped for 7 days and there are 40 days in total to complete the job, then the remaining number of days to work is 40 - 12 - 7 = 21 days. If the contractor can complete the job with 15 people in 40 days, then to complete the job in 21 days, he needs to add 15 / 40 * 21 = 8.25 more workers. Since it is not possible to add a fraction of a worker, the contractor needs to add at least 9 more workers to the team to complete the job on time.
Semoga dengan pertanyaan yang sudah terjawab oleh stefanaldrich123 dapat membantu memudahkan mengerjakan soal, tugas dan PR sekolah kalian.
Apabila terdapat kesalahan dalam mengerjakan soal, silahkan koreksi jawaban dengan mengirimkan email ke yomemimo.com melalui halaman Contact
Last Update: Sat, 08 Apr 23